Create the Gantt Chart for the following Task Table. Also identify the
critical path for this activity.
|
Task |
Duration (days) |
Depndencies |
|
T1 |
8 |
|
|
T2 |
15 |
|
|
T3 |
15 |
T1 |
|
T4 |
10 |
|
|
T5 |
10 |
T2,T4 |
|
T6 |
5 |
T1, T2 |
|
T7 |
20 |
T1 |
|
T8 |
25 |
T4 |
|
T9 |
15 |
T3, T6 |
|
T10 |
15 |
T5, T7 |
|
T11 |
7 |
T9 |
|
T12 |
10 |
T11 |