Group Homework 1 (Due Wednesday 3 August 2548)


Create the Gantt Chart for the following Task Table.  Also identify the critical path for this activity.


Task

Duration (days)

Depndencies

T1

8

 

T2

15

 

T3

15

T1

T4

10

 

T5

10

T2,T4

T6

5

T1, T2

T7

20

T1

T8

25

T4

T9

15

T3, T6

T10

15

T5, T7

T11

7

T9

T12

10

T11